Thanks to Ed for photos |
Sunday, 28 July 2013
Friday, 26 July 2013
Thursday, 18 July 2013
Foundations Progress
Wednesday, 17 July 2013
Cantilever base, retining wall concrete and BRICKS
Base of foundation ready for concrete This beam will support the cantilever slab |
Retaining wall cast - not sure how the digger gets off the island! |
Monday, 15 July 2013
First Concrete Pour
Base concrete for the retaining wall to the high end of the site - pavement on the left and sloping yard to the rear.
Rear wall of the workshop with stepped reinforcement in place for the second pour of waterproof concrete.
The old concrete yard to the rear and old workshop slab to the right is being left in place to provide a storage area and avoid disturbing the neighbouring foundations.
Preparing the trench for the cantilever slab to support the new blockwork alongside the party wall |
Thursday, 11 July 2013