Thursday 27 February 2014

27 Feb - Doors & Electricity

We have electricity! so the generator will soon go and yesterday the sliding door installation on the 2nd floor was completed.  The permanent JCB is due to leave site next week with only occasional visits for the remainder of the contract to the joy of most neighbours (noise & parking) and disappointment of children who will miss the shiny Tonka toy from the school run. 
Staircase steels due soon and some stripping of unspecified paint from existing steels. 
Agreed ceramic floor tile layouts and details this morning and happy that Kate Moss's ex boyfriend is laying them.

For a change the sun is shining today so everyone is uplifted.  It will be great to complete the insulated render and be 100% watertight.
2nd Floor


2nd floor landing





First floor living room





2nd floor landing looking down to 1st & Grnd
2nd floor landing






1st floor landing
1st floor landing
Ground floor stairwell looking up

Electricity!
Workshop




Sunday 16 February 2014

14 February

Train + bike + rain visit to steelwork fabricator in Yeovil


Yeovil Pen Mill Station




13 February



Workshop

First Floor Corridor


2nd floor stair landing